Skip to content
Archive of posts tagged 38th/Blake Station

FasTracks Progress: 38th and Blake

Last time we checked in with FasTracks, we caught a glimpse of full speed testing for the A-Line. Now, with exactly two months until its grand opening, we can start to see the elements of this huge transit project finishing up. For this post, we are going to visit the 38th and Blake commuter rail station, with a healthy load of pictures.

Let’s start out with photos of the station itself. Here we can see some notable differences right off the bat. The overhead catenary system is much more robust than the light-rail system we are all used to seeing. The tracks are also lowered to allow level boarding on the commuter rail vehicles.

2016-02-21_38thBlake-06 2016-02-21_38thBlake-02

So how did we get down on the tracks for these photos? At each end, there are track-level crossings to get to each side of the station. There is also a pedestrian bridge to get you across, which we will cover in depth later this week.

2016-02-21_38thBlake-11 2016-02-21_38thBlake-12

The 38th and Blake station is the first stop outside of Downtown Denver to get to the airport. We were very lucky to have a clear day, and a double stacked freight train parked right outside the station.

2016-02-21_38thBlake-03 2016-02-21_38thBlake-05

Outside of the commuter rail station, great improvements have been made to the pedestrian environment. Wider sidewalks and sheltered bike parking are two significant improvements.

2016-02-21_38thBlake-08 2016-02-21_38thBlake-07

Need I say more? New train stations are exciting!

2016-02-21_38thBlake-04 2016-02-21_38thBlake-10

You could say I had a great time taking photos around this station.

2016-02-21_38thBlake-13 2016-02-21_38thBlake-14

I’m sure I am the first to lay down on the yellow caution line and take this unique perspective of the station.


In two months, the 38th and Blake station will be fully operational, helping service trains to Denver International Airport. We, here at DenverUrbanism, couldn’t be more excited!

East Rail Line Progress – 38/Blake Station and 40th Avenue Work

By Robert Wilson

Progress along the East Rail Line has been slow and steady over the winter months. Some significant progress has been on a number of bridges (18 currently under construction). The majority of the work over the winter months, however, has been less noticeable utility relocation work and preliminary construction that will allow for a very busy spring and summer construction schedule on our line out to DIA.

Between Denver Union Station (DUS) and the the first stop (38/Blake) the final overhead catenary system (OCS) foundations have been installed while basic utility work is being completed. The ground here is graded, compacted, and nearly ready for construction of the station and track installation.


Crews have completed the girder placement for the 38th Avenue Bridge just north and east of the 38th/Blake Station site. Construction crews closed 38th Avenue over night in December to install the load baring girders and have since completed the abutment connections. Over the next few months, crews will continue working on the bridge while a a pedestrian bridge is designed just to the northeast prior to 2016 to connect the park-n-ride lot with the station platform. 38th Avenue will likely be closed a few more times before this bridge is completed. However, these closures usually occur at night so its impact to traffic should be minimal.


One road closure that has been the exception to that statement has been 40th Avenue, which is still closed between Walnut and Josephine Street and will be for the next year. Where the paved 40th Street was just a few months ago crews have excavated twenty feet down to install an upgraded fiber optic network, a new sanitary sewer system and storm sewers. In the coming months crews will continue implementing drainage improvements and reconstruct 40th Avenue in concrete (complete with 8 foot sidewalks on the south side of the street) allowing for the East Rail Line to be constructed on the north side. The new 40th Avenue will be an interesting streetscape design as there will be no pedestrian space along the north side of 40th Avenue, unlike its pre-construction state (if you can call a dirt pad for bus stops a pedestrian space). This will keep all pedestrian and bicycle traffic on the south side of 40th Avenue. 40th Avenue should open again to traffic sometime early next year.



Very large (more than ten feet tall) box culverts will form the foundation of the new sanitary sewer system underneath 40th Avenue. Crews are hard at work completing the improvements, however, construction of this magnitude will take time.



For a sense of scale, check out the tractor next to the box culverts.

The culverts interlock and seal – just like giant blocks complete with a rubber seal.


Next, we will take a look at the progress at the Colorado Station and the Quebec Bridge approaching Stapleton.